South Central Texas Crushed Stone Processing and Rail Load Out Facility

Location: South Central Texas

Type: Aggregate

Pounds of rebar: 1,983,108 lbs.

Anchor bolts: 3,304

Completion: 2020

Description

We constructed this state-of-the-art facility from the ground up — one of the largest within its organization. Serving as the heartbeat of the operation lies the main crusher foundation, feeding a half-mile conveyor line elevated on 53' tall pedestals. This foundation symbolizes the intricate planning and execution that define this project. Additionally, we constructed a 260' long surge tunnel and a 380' long blending tunnel. The scope included foundations for radial stackers, freshwater and thickener tanks, sand plant, and various ancillary equipment essential for operations.

More Projects

South Central Texas Crushed Stone Processing and Rail Load Out Facility

Location: South Central Texas

Type: Aggregate

Pounds of rebar: 1,983,108 lbs.

Anchor bolts: 3,304

Completion: 2020

Nucor Steel Plate Mill

Location: Brandenburg, KY

Type: Heavy Industrial

Yards of concrete: 1,722

Pounds of rebar: 239,838

Anchor bolts: 428

Completion: June 2023

South Central Texas Frac Sand Plant

Location: Tolar, TX

Type: Aggregate

Pounds of rebar: 1,342,2oo lbs.

Anchor bolts: 1812

Completion: 2019